There is no single answer to "which AGV should we buy"
-
Scenario A: Standard, repetitive transport in a defined space
-
Scenario B: Mixed workflows with variable routing and load types
-
Scenario C: Scaling from a successful pilot
-
Scenario D: Retrofitting an existing, live warehouse
-
How to figure out which scenario you are in
There is no single answer to "which AGV should we buy"
If you call five AGV manufacturers with the same question, you will get five different answers—and each one will be based on the assumption that their product fits your operation. That is a sourcing problem, not a technology problem.
I have been on the procurement side of this for about six years now. When I audited our 2023 spending on material handling, I found that roughly 40% of what we had budgeted as "AGV cost" was actually infrastructure, integration, and software fees. The vehicle itself was the cheap part. Most buyers never see this coming because the quote is structured around the hardware.
Here is the honest version: the right sourcing strategy depends entirely on which of four situations you are actually in. I will walk through each one, the cost profile I have seen in practice, and the specific trap that tends to show up.
Most buyers focus on per-vehicle pricing and completely miss the integration, charging infrastructure, and software licensing that can add 30-50% to the total. The question everyone asks is "what is the unit cost?" The question they should ask is "what is included in that unit cost, and what gets billed separately?"
Scenario A: Standard, repetitive transport in a defined space
This is the classic case. You have a warehouse with fixed pick-and-drop points, predictable routes, and the same kind of load moving back and forth all day. Maybe it is raw material from receiving to the production line. Maybe it is finished pallets from the end of the line to shipping.
In this scenario, the sourcing question is straightforward, and I mean that fairly literally. You are buying, more or less, a commodity. The vehicle class is well understood, the routes are easy to map, and you do not need a lot of system logic. Your lever is the vendor network and the per-unit terms.
Cost profile I have seen: the vehicle becomes a smaller share of the total than you would think, but the infrastructure is predictable. Charging stations can be quoted on a per-vehicle basis. The software is usually a basic fleet manager, and you can negotiate a multi-year license that brings the annual cost down.
The trap: "standard" does not mean the same thing to every vendor. In my first year of doing this, I assumed standard meant standard. It did not. One vendor's "standard" payload was 500 kg. Another's was 1,000 kg, but with a rule that payload above 800 kg required a different drive unit at a different price. I cost us a $600 redo on a spec sheet before I learned to write the acceptance criteria myself.
If you are in Scenario A, the sourcing move is to get quotes from a vetted manufacturer network, keep the spec tight, and negotiate hard on the foundation items—chargers, spare parts kits, and the first-year maintenance contract.
Scenario B: Mixed workflows with variable routing and load types
This is where sourcing gets expensive, and honestly, most of the cost problems I have seen come from buyers who did not realize they were in Scenario B until after they signed.
In Scenario B, you have multiple load types. Maybe it is pallets and totes and a few carts. Maybe the routes change based on order volume. Maybe there is human traffic that the vehicles have to work around, or the layout is not perfectly rectangular. Whatever the specifics, the system logic has to do more work, and the sourcing question shifts from "which vehicle" to "which integrator."
I should be honest about this: I am not 100% sure I would call this a vehicle purchase at all in Scenario B. What you are really buying is a systems integration project with a hardware component. The vehicle is the visible part. The money is in the routing software, the traffic management, the interfaces to your WMS, and the commissioning hours.
Cost anchor, rough: across the quotes I have compared in the last 18 months, integration and software typically run 2-4x the vehicle cost in a true Scenario B deployment. Take that with a grain of salt—it depends a lot on how many systems you are tying into—but the pattern has held in every case I have tracked.
The trap here is the reverse of Scenario A. If you try to source Scenario B like Scenario A—lowest unit price, tight hardware spec—you will get a system that works in the demo and falls apart when your order profile shifts. I have seen that movie. A vendor matched a competitor's per-vehicle price, then charged for every change order during commissioning. The total came in 22% over the original budget, and the savings on the vehicles were about 3%.
If you are in Scenario B, your sourcing strategy should be weighted toward integration partners with a proven track record in your industry, not the lowest hardware quote.
Scenario C: Scaling from a successful pilot
You ran a three-vehicle pilot, it worked, and now you want to expand to 30 or 50 vehicles across the site. This is where the cost math changes in a way that surprises people.
The vehicles do not get proportionally cheaper. Do not hold me to this, but in my experience the per-vehicle price in a 50-vehicle order is usually within 10-15% of the pilot price—volume discounts on AGV hardware are smaller than in most capital equipment categories because the market is still fragmented.
Where the savings show up is on the fixed costs. Software license, one-time setup, integration architecture, and project management get amortized across a much larger fleet. That is real, and it can be significant.
Where the costs show up is in infrastructure. Floor marking or SLAM maps need to be extended. Charging becomes a facility problem. WiFi coverage gets tested in ways your pilot never tested it. And the maintenance contract pricing changes category.
The trap: the "cheap" pilot was never the real cost per unit. I have watched procurement teams celebrate a great pilot price and then get blindsided by the scale-up quote—not because the vendor was dishonest, but because the pilot was scoped to prove value, not to represent full production conditions. The pilot ran on a dedicated loop with marked floors and no human traffic. Production had none of those things.
If you are in Scenario C, the sourcing move is to get the vendor to quote the production scope, not the pilot scope, before you celebrate anything. And ask specifically what infrastructure was excluded from the pilot pricing.
Scenario D: Retrofitting an existing, live warehouse
This is the one where the cost surprises tend to be the largest, and I will be blunt: it is the scenario most buyers underestimate.
In a greenfield build, the warehouse is designed around the AGV fleet from day one. In a retrofit, the building has opinions. The floor has slopes. Columns are where columns are. The aisles were sized for forklifts and the WiFi was sized for barcode scanners.
Cost profile here is dominated by the things that are not the AGV. Floor remediation, charging infrastructure placement (and the electrical work to support it), WiFi densification, safety sensor retrofits, and the project management to keep all of that coordinate while the warehouse keeps shipping.
I am not going to give you a percentage for how much floor remediation adds, because the range is too wide to be useful. I will say this: in the two retrofit quotes I compared most recently, the infrastructure line items were larger than the vehicle line items in both cases. That is not universal, but it is common enough that you should plan for it.
The trap: infrastructure quotes are frequently "allowance" based. An allowance is not a price. It is a placeholder. Get the allowance lines itemized before you sign, and get the vendor to specify what happens if the actual cost exceeds the allowance.
If you are in Scenario D, your sourcing strategy needs to weight infrastructure certainty much harder than vehicle price. A 5% higher vehicle cost with a firm infrastructure quote is usually the better deal than a 5% lower vehicle cost with a soft allowance.
How to figure out which scenario you are in
If you take nothing else from this, take this: figure out your scenario before you take a single quote. The quote structure tells you nothing about which one you are in—it just tells you what the vendor wants to sell.
Here is the quick diagnostic I use now, after getting burned on this twice:
- If your routes are fixed and your load types are standard—you are in Scenario A. Optimize for vendor network, per-unit cost, and tight specs.
- If your routes vary, your load types vary, or you need interfaces to multiple existing systems—you are in Scenario B. Optimize for integrator track record, and budget 2-4x the vehicle cost for the rest of it.
- If you have a working pilot—you are in Scenario C. Get the production-scope quote before you get excited about the pilot numbers.
- If your warehouse is already full of things you cannot move—you are in Scenario D. Get infrastructure cost certainty before vehicle price optimization.
And if you are honestly not sure, that usually means you are in B or D. Scenario A and C are pretty obvious when you are in them. The ambiguous cases are almost always the expensive ones.
One last thing—on efficiency. I have watched the shift toward AGVs across our sites over the last few years, and the operations that do well with it are not the ones that got the lowest quote. They are the ones that matched the sourcing strategy to the actual scenario, planned the infrastructure line honestly, and accepted that the vehicle is the cheap part. That last bit is the hardest one for procurement people, myself included, to internalize.