Who this checklist is for
-
Step 1: Write your load and traffic profile before you open a single vendor tab
-
Step 2: Verify the safety certification itself, not the word "certified"
-
Step 3: Kill the "same specification" trap on your comparison sheet
-
Step 4: Run a small first order—and treat it as a real test, not a formality
-
Step 5: Do the site visit and a blind reference call
-
Step 6: Get integration and support scope in writing
-
Step 7: Run a written FAT before the unit ships
-
Common mistakes that cost you a redo
Who this checklist is for
Quick version: if you're sourcing an automated guided vehicle (AGV) system—or a single unit to test the waters—and you don't want to eat a redo, this is the 7-step checklist I run before any purchase order goes out. I work as a quality and compliance manager. I review AGV specifications and vendor packages before they reach our facilities—roughly 180 to 220 packages a year. In 2025 alone I rejected about a third of first deliveries. Not because the automated guided vehicle manufacturers were bad. Because the vetting upstream was shallow.
This isn't a "how AGVs work" article. It's the exact sequence I use to keep loose specs, mismatched models, and optimistic sales decks from turning into a $40,000 mistake. Seven steps. Follow them in order—the order actually matters, because each step feeds the next.
Step 1: Write your load and traffic profile before you open a single vendor tab
The most common mistake I see is starting with the question "which automated guided vehicle manufacturers should I talk to?" Wrong starting point. Start with what you actually need to move.
- Load weight, footprint, and center of gravity—best case and worst case
- Floor conditions: flat, ramps, thresholds, expansion joints, dock edges
- Route assumptions: one-way vs. bi-directional, mixed pedestrian traffic, aisle width
- Existing WMS, WCS, or ERP systems—because integration isn't an afterthought, it's a spec line
This profile becomes your comparison sheet later. Every vendor gets scored against the same document. If your automated guided vehicle warehouse requirements quietly change between vendor calls, you're not comparing anything—you're shopping. There's a difference, and it costs money.
Step 2: Verify the safety certification itself, not the word "certified"
Here's where I got burned once and won't again. "ISO certified" means almost nothing until you read the scope. A company can hold ISO 9001 and still not have a single AGV model verified against a driverless-vehicle safety standard.
For AGVs, the two anchor references worth asking about are ANSI/ITSDF B56.5 (safety standard for driverless, automatic guided industrial vehicles) and ISO 3691-4:2020 (safety requirements and verification for driverless industrial trucks and their systems). Ask for:
- The actual certificate or declaration of conformity—not a screenshot from the brochure
- The certificate scope: does it name the specific model you're buying?
- Which edition or year the verification was done against
If a supplier can't produce the model-level document, that's not a red flag. It's a stop sign.
Why is this step two? Because safety verification is the one thing the sales deck can't fix after the fact. Either the model has the paperwork, or it doesn't.
Step 3: Kill the "same specification" trap on your comparison sheet
I assumed "same specifications" meant identical results across vendors. Didn't verify. Turned out each had a slightly different interpretation of repeatability, navigation tolerance, and battery swap time. We compared three documents that looked identical on paper and quoted three materially different machines.
The fix is to rigidize the sheet itself. Same units. Same measurement points. Same acceptance criteria. If a vendor lists "load capacity: 1,500 kg," ask whether that's the deck rating, the drive-train rating, or the rated load at full slope. Those are three different numbers with three different implications for your automated guided vehicle deployment. Same phrase, different reality—and you only find out at the loading dock.
It took me about four years and 120-plus vendor evaluations to understand that the comparison sheet is the actual product decision. Everything upstream of it is marketing.
Step 4: Run a small first order—and treat it as a real test, not a formality
This is where I split from a lot of my procurement peers, and I'll say it plainly: a small first order isn't a red flag. It's the correct way to vet a manufacturer you haven't worked with. Any vendor that rolls its eyes at a single-unit or small pilot is telling you exactly how they handle every order that comes after the deal closes.
When I was starting out on the buyer side, the vendors who treated a small, awkward first order seriously were the ones we still call for the big deployments. The ones who wanted the big purchase order first and the pilot "later"—those are the ones we don't call back. Small doesn't mean unimportant. It means potential.
Use the pilot to test three things: does the unit actually meet the spec, does the support person answer the phone on a Tuesday afternoon, and does the vendor treat your small order like a real order. That third one is subjective. It's also the most accurate predictor of the next three years.
Step 5: Do the site visit and a blind reference call
The edited factory tour is not a site visit. I've watched a world-class video walkthrough of a facility and then stood on the actual floor and seen a rework bin that no camera angle caught. Everyone told me to insist on an in-person visit for automated guided vehicle systems. I didn't, once. The line I approved on video had scrap and rework that only showed up in the audit report I read months later.
For references, ask for two clients you can call without the vendor on the line. Then ask three questions: what broke first, how long did spare parts take, and would you buy again. The answer to the first question tells you more than the entire brochure. Does that sound obvious? It is. It's also skipped constantly.
Step 6: Get integration and support scope in writing
AGVs are systems, not boxes. If the interface isn't documented, you're not buying an automated guided vehicle system—you're buying a machine you'll have to hand-integrate at your own cost, on your own timeline.
Get these in writing before the PO goes out:
- Interface specification—API, protocol, or hardware handshake, in enough detail for your IT team to review
- Who owns the integration work, and what the acceptance test looks like
- Spare parts lead times and the support SLA—response time, not just a phone number
- Who performs routine maintenance, and whether remote diagnostics are included or extra
"We'll figure that out during deployment" is not a scope of work. It's a change order waiting to happen.
Step 7: Run a written FAT before the unit ships
We didn't have a formal Factory Acceptance Test checklist for our first two automated guided vehicle purchases. Cost us when the delivered unit passed "visual inspection" but failed a simple repeatability test on our real floor. After the third round, I finally built a pass/fail sheet. Should have done it after the first time.
The FAT sheet should list every spec point from Step 1 with a measurable pass/fail. Include a live load test on your actual duty cycle—not the vendor's demo loop. Sign off in writing. Any claim of "within tolerance" without a defined tolerance written into the contract is not acceptable, and it's the single most expensive phrase in this industry.
Common mistakes that cost you a redo
- Confusing company-level ISO with model-level safety verification. They're different documents with different scopes—check the one you actually need.
- Skipping the pilot because it's \"small.\" Small is exactly when mistakes are cheap to find.
- Accepting \"within industry standard\" as an answer. Ask which standard, which edition, which measurement.
- Signing a spec sheet with no acceptance criteria. If it's not testable, it's not a spec—it's a hope.
- Letting the comparison sheet drift between vendors. One document, one scoring rubric, all vendors, every time.
Simple to say. Rarely done. But every one of these steps came out of a delivery I had to reject, and the fix each time was process—not a different vendor.